What happened
TC Energy Corporation (NYSE: TRP) outlined a proposed Alberta Growth Connector and said NGTL demand is forecast to reach approximately 18 Bcf/d in 2031.
The plan also points to additional service offerings as early as Jan. 2027, which gives the filing a dated commercial milestone investors can track.
The proposed Alberta Growth Connector would run about 370 kilometres on a 48-inch west-to-east route, linking growing Western Canadian supply to Alberta's oil sands region via NGTL.
TC Energy said the broader proposed facility plan also includes additional pipeline loops and compressor units across the integrated NGTL-ATCO System.
The forecast implies a larger system than the 14.4 Bcf/d demand view for 2026 that the filing uses as its baseline.
Why it matters
The forecast rises by 3.6 Bcf/d over the five-year period, a change that points to more throughput demand for the NGTL System if the plan advances.
TC Energy said more than 60% of the increase is expected from Alberta's oil sands, power generation and data centre sectors, which ties the growth plan to specific end markets.
The company also said the 2031 view is about 1.5 Bcf/d above the outlook in the 2025 NGTL System Annual Plan, so the demand case has moved higher since that earlier plan.
The Alberta Growth Connector would initially add about 1 Bcf/d of capacity, with the ability to expand further as customer needs develop.
Over the past decade, TC Energy has invested more than $15 billion in the NGTL System, lifting its rate base from approximately $6 billion to nearly $19 billion.
It is also advancing approximately $1.2 billion of sanctioned NGTL expansion projects, so the filing shows both a larger base and more projects already moving ahead.
The proposed Alberta Growth Connector and related facilities still need commercial support, engagement with rightsholders and stakeholders, regulatory approvals and TC Energy's project-sanctioning process.
What's next
The next dated checkpoint is additional service offerings as early as Jan. 2027.
Customer commitments at that point would strengthen the growth case, while weak uptake would leave the commercial-support hurdle in place.